Go Live Implementation of Web-Based Energy Management Application Navitas

15.06.2015
|
0 Comments
|
NAVITAS

This post is also available in: Indonesian

HOUSED in the Centre Of Excellence PT PJB Services, Jl. Raya Juanda No. 17, Sidoarjo, on Friday, May 22, 2015 has been implemented Go Live Implementation of Energy Management Web-Based Applications – Navitas for the management of operation and maintenance services unit of PT PJB Services. For the first phase, the implementation of Navitas done in three units of O & M services, namely:
1. 3 Bangka Belitung power plant (2 x 30 MW),
2. East Gili power plant (20 MW),
3. Asahan hydropower I (2 x 90 MW).
 
Go Live Navitas for Unit 3 was attended by Hari Monoarfa as President Director of PT PJB Services, the Board of Directors of PT PJB Services, Operations Directorate Managers and colleagues Management O & M.
 
Go Live Navitas opened with a speech Director PJBS Today Suharso, then followed by a speech from the Director of Operations Ompang Riski Hasibuan. The event continued with the demo Navitas implementation of each unit (3 Bangka Belitung power plant, power plant and hydropower Duri Asahan I)
 
Energy Management Web-based applications – Navitas, on the run with Workflow scheme with the processing or monitoring:
1. Realization of Production – Use Self – Losses Transformers – Sales
2. Realization of Operating Performance Indicators
3. Realization of Fuel – hydrology
4. The realization of expense
 
Other operating data related to business processes PJBS otherwise known as Production Monitoring such as:
1. Equipment crucial
2. Plan target annual performance operation
3. Operation Plan Daily – Weekly – Monthly
4. Plan of Fuel – Hydrology.
 
Of Navitas we can retrieve data from each unit in the time period daily, weekly and monthly which will allow everyone concerned to know the performance of a plant.
 
After the Go Live Navitas on three units, will continue the set-up the implementation of Navitas at O ​​& M services unit of PT PJB Services else:
1. Banjarsari power plant of 2 X 110 MW,
2. Amurang power plant of 2 X 25 MW,
3. Nii Tanasa Kendari plant of 2 X 10 MW,
4. Bolok power plant of 2 X 16.5 MW,
5. 4 Bangka Belitung power plant of 2 X 16.5 MW,
6. The power plant of 2 X 7 MW Ropa,
7. Tidore power plant of 2 X 7 MW.